MDOT Contracts Advertised for a April 28, 2009 letting.
Click Call # to Email a Question
CallDescriptionProposalEBSx FileAddendaEBSx AmendFuel PricesBid ListCadd FilesPlan IndexPermit DocBid Tabulations
01 Upgrading approximately 5 miles of US Highway 78 in Tupelo, known as Federal Aid Project No. NH-0006-03(037) / 104095310, in the County of Lee, State of Mississippi.
Project Completion: 001
Fax1
02 Withdrawn
Mill and Overlay from Edwards St. to 31st. Avenue, known as Federal Aid Project No. STP-0080-01(015) / 105453301, in the County of Forrest, State of Mississippi.
Project Completion: 002
03 Overlaying approximately 5 miles of US Highway 98 at Tylertown, known as Federal Aid Project No. NH-0014-02(061) / 105472301, in the County of Walthall, State of Missisippi.
Project Completion: 003
04 Grading, draining and bridge work necessary to add 2 lanes to SR 8 between Cleveland and Ruleville, known as Federal Aid Project Nos. STP-0016-01(029) / 102155301 & 302, in the Counties of Bolivar & Sunflower, State of Mississippi.
Project Completion: 004
1
Fax1
1
05 Construction necessary to replace the bridge on SR 15, between SR 19 and the Winston County Line, known as Federal Aid Project No. BR-0022-02(049) / 104632301, in the County of Neshoba, State of Mississippi.
Project Completion: 005
1
1
06 Widening and overlaying approximately 11 miles of SR 1 north of Rosedale, known as Federal Aid Project No. STP-0043-02(015) / 105436301, in the County of Bolivar, State of Mississippi.
Project Completion: 006
07 Installing signs at the I-10/SR 67 Interchange, known as Federal Aid Project No. STP-0064-01(026) / 101208304 & 305, in the Counties of Harrison & Jackson, State of Mississippi.
Project Completion: 007
Fax1
08 Replacing a bridge on SR 29 at Black Creek, known as Federal Aid Project No. BR-0224-00(034) / 100775301, in the County of Perry, State of Mississippi.
Project Completion: 008
09 Overlaying approximately 13 miles of SR 493 between the Lauderdale County Line and SR 16, known as Federal Aid Project No. STP-0447-00(018) / 105426301, in the County of Kemper, State of Mississippi.
Project Completion: 009
10 Overlaying approximately 9 miles of SR 438 between SR 1 and US 61, known as Federal Aid Project No. STP-0622-00(027) / 105485301, in the County of Washington, State of Mississippi.
Project Completion: 010
11 Traffic signal installation at the intersection of US Hwy 80 and Shaw Road, known as Federal Aid Project No. STP-7314-00(022) / 105380301, in the County of Hinds, State of Mississippi.
Project Completion: 011
1
1